On September 27, 2011 at 2:00 p.m. in the District Office bids were received from general contractors interested in constructing our elementary building project. Four general contractors from the surrounding area submitted base and alternate bids to be opened. They were:
Company Location Base Bid Alternate 1-8 Total Total Project
Cardinal Const. Waterloo $7,617,000 $691,000 $8,308,000
Garling Const. Cedar Rapids $8,063,000 $657,000 $8,720,000
Larson Const. Independence $7,865,000 $757,000 $8,622,000
Portzen Const. Dubuque $7,998,000 $648,600 $8,647,100
The eight alternate items that were outside the base bid and bid separately were:
Alternate #1 - Add two preschool classrooms as per design drawings
Alternate #2 - Add two upper elementary classrooms as per design drawings
Alternate #3 - Add additional casework to classrooms
Alternate #4 - Add access control and monitoring of existing building
Alternate #5 - Add video surveillance of existing building
Alternate #6 - Additional site work
Alternate #7 - Receive a deduction if vinyl flooring is used instead of terrazzo in corridors
Alternate #8 - Add solar control using shading devices for window system
We selected alternates #1, #6, and #7 which was a total of an additional $270,000 bringing the total cost of construction for the elementary project to $7,877,000. Our construction budget for the project after deducting the cost of planning, design, and the construction process is approximately $7,400,000 leaving the project over budget by approximately $487,000.
With the project coming in over budget no contract was issued at this time. It was recommended that the bids and elementary project be reviewed by OPN and the district to determine what options are available to proceed with the project.